Solana Highlands Modernization Project
If you have questions regarding the Solana Highlands Modernization project - please call 858-794-3699 or email facilities@sbsd.k12.ca.us
Update 12/1/2017Construction work is coming to a close at Solana Highlands. The food service department moved into the new service kitchen on 11/17/2017.MARK YOUR CALENDARS! We are pleased to announce a ribbon cutting ceremony scheduled for 1/12/2018 in conjunction with the already scheduled All School Assembly at 8:35 am.Update 11/2/2017Construction work continues in the student food service kitchen. Estimated completion is scheduled for the first week of December.It is now necessary to test the fire alarm to add the student Service kitchen to the school system. Testing will take place shortlyafter 8:00 am on Saturday, November 4, 2017. We apologize in advance for any inconvenience this may cause.Update 10/7/2017Construction work continues in the student food service kitchen.Landscape in front of school is near completion. Artificial turf at front seat wall and kindergarten play area is complete.Concrete at the seat wall at kindergarten lunch area will be completed Saturday.Fencing in front of classrooms is underway.
Update 9/18/2017The administrative offices are now open and staff is settled.The office staff are scheduled to occupy the new administration offices on Wednesday, September 13, 2017. Watch for communication from the Solana Highlands Principal the week of September 11.The student kitchen remains under construction. Expected completion late-October.Update 8/28/2017Welcome back everyone. So glad to see everyone at the Solana Highlands Mini Open House today. We are ready for the 2017-18 school year. Thank you for your patience through the continuing modernization project. The administration and student service kitchen remain under construction while the rest of the campus is ready for students.
Update 8/4/2017The revised framing of the interior areas, entrance, and student kitchen as well as site work, the installation of new lunch shelters, replacement of air conditioning units, replacement of roof with standing seam metal, and systems upgrades are well underway.Update 6/23/2017Construction is underway at Solana Highlands. Packing and moving of all materials and furniture is complete and new flooring is being installed. Demolition of the administration and the new child nutrition services kitchen began the week of 6/19/2017. We expect the delivery of various supplies in the next few weeks (e.g. heating and air conditioning units, appliances, roofing materials, etc.).The Administrative office, temporarily located in Room 12 is closed for the summer. Office staff return to Room 12 Monday, August 7th. If you have questions regarding registration, please contact the District Office at 858-794-7100.If you have questions regarding the Solana Highlands Modernization project - please call 858-794-3699 or email facilities@sbsd.k12.ca.usThe timeline for modernization of the Solana Highlands campus is as follows.This aerial photo shows the existing campus.This graphic shows the areas of the new campus that will be remodeled.Here is the detail of the areas to be remodeled.Here are the changes planned for the entry and office area.These images show how the front of the campus will change.The kitchen will be remodeled and expanded.In addition to the remodeled areas, there will be upgrades to the entire campus.Solana Highlands also has a new garden which will be completed in Spring 2017.