• Solana Highlands Modernization Project

    If you have questions regarding the Solana Highlands Modernization project - please call 858-794-3699 or email facilities@sbsd.k12.ca.us


    Update 12/1/2017
     
    Construction work is coming to a close at Solana Highlands. The food service department moved into the new service kitchen on 11/17/2017. 
    MARK YOUR CALENDARS! We are pleased to announce a ribbon cutting ceremony scheduled for 1/12/2018 in conjunction with the already scheduled All School Assembly at 8:35 am.
     
    Food service serving line

    Update 11/2/2017
     
    Construction work continues in the student food service kitchen. Estimated completion is scheduled for the first week of December.
    It is now necessary to test the fire alarm to add the student Service kitchen to the school system. Testing will take place shortly
    after 8:00 am on Saturday, November 4, 2017. We apologize in advance for any inconvenience this may cause.
     
    Student Service Kitchen Equipment
     

    Update 10/7/2017
     
    Construction work continues in the student food service kitchen.
    Landscape in front of school is near completion. Artificial turf at front seat wall and kindergarten play area is complete.
    Concrete at the seat wall at kindergarten lunch area will be completed Saturday.
    Fencing in front of classrooms is underway.
     
    Rough in work at kitchen ceiling   front landscape
     

    Update 9/18/2017
     
    The administrative offices are now open and staff is settled.
     
    Lunch Canopy north of building   Entrance
     
     
     
    Update 9/9/2017
     
    The office staff are scheduled to occupy the new administration offices on Wednesday, September 13, 2017. Watch for communication from the Solana Highlands Principal the week of September 11.
    The student kitchen remains under construction. Expected completion late-October.
     
    2x4 stud wall at student kitchen service line

     Update 8/28/2017
     
    Welcome back everyone. So glad to see everyone at the Solana Highlands Mini Open House today. We are ready for the 2017-18 school year. Thank you for your patience through the continuing modernization project. The administration and student service kitchen remain under construction while the rest of the campus is ready for students.

    Media Center at Solana Highlands    Court Yard at Solana Highlands    Kindergarten play area with artifical turf


     Update 8/4/2017
     
    The revised framing of the interior areas, entrance, and student kitchen as well as site work, the installation of new lunch shelters, replacement of air conditioning units, replacement of  roof with standing seam metal, and systems upgrades are well underway. 
     
    Newly framed front entrance of school
     
    Update 6/23/2017
     
    Construction is underway at Solana Highlands.  Packing and moving of all materials and furniture is complete and new flooring is being installed. Demolition of the administration and the new child nutrition services kitchen began the week of 6/19/2017.  We expect the delivery of various supplies in the next few weeks (e.g. heating and air conditioning units, appliances, roofing materials, etc.).
     
    The Administrative office, temporarily located in Room 12 is closed for the summer. Office staff return to Room 12 Monday, August 7th. If you have questions regarding registration, please contact the District Office at 858-794-7100.
     
    If you have questions regarding the Solana Highlands Modernization project - please call 858-794-3699 or email facilities@sbsd.k12.ca.us
     
     

     
    The timeline for modernization of the Solana Highlands campus is as follows.
     
     
    Solana Highlands Timeline
     
    This aerial photo shows the existing campus.
     
    Solana Highlands Existing
     
    This graphic shows the areas of the new campus that will be remodeled.
     
    Solana Highlands Remodel
     
    Here is the detail of the areas to be remodeled.  
     
    Solana Highlands Remodel detail
     
    Here are the changes planned for the entry and office area.
     
    Solana Highlands Office Detail
     
    These images show how the front of the campus will change.
     
    Solana Highlands new front
     
    The kitchen will be remodeled and expanded. 
     
    Solana Highlands Kitchen
     
    In addition to the remodeled areas, there will be upgrades to the entire campus. 
     
     
    Solana Highlands Upgrades  
     
    Solana Highlands also has a new garden which will be completed in Spring 2017.
     
    Solana Highlands Garden