Solana Highlands Modernization Project

Update 6/23/2017
Construction is underway at Solana Highlands.  Packing and moving of all materials and furniture is complete and new flooring is being installed. Demolition of the administration and the new child nutrition services kitchen began the week of 6/19/2017.  We expect the delivery of various supplies in the next few weeks (e.g. heating and air conditioning units, appliances, roofing materials, etc.).
 
The Administrative office, temporarily located in Room 12 is closed for the summer. Office staff return to Room 12 Monday, August 7th. If you have questions regarding registration, please contact the District Office at 858-794-7100.
 
If you have questions regarding the Solana Highlands Modernization project - please call 858-794-3699 or email facilities@sbsd.k12.ca.us
 
 
 
The timeline for modernization of the Solana Highlands campus is as follows.
 
SH Timeline
 
This aerial photo shows the existing campus.
 
SH Existing
 
This graphic shows the areas of the new campus that will be remodeled.
 
SH Remodel
 
Here is the detail of the areas to be remodeled.  
 
SH Remodel detail
 
Here are the changes planned for the entry and office area.
 
SH Office Detail
 
These images show how the front of the campus will change.
 
SH new front
 
The kitchen will be remodeled and expanded. 
 
SH Kitchen
 
In addition to the remodeled areas, there will be upgrades to the entire campus. 
 
SH Upgrades  
 
Solana Highlands also has a new garden which will be completed in Spring 2017.
 
SH Garden  
 