• Skyline Reconstruction Information and Frequently Asked Questions (FAQ)

    Solana Beach School District has been working on plans for the reconstruction of its oldest campus, Skyline School. The reconstruction of this facility, which is over 60 years old, is the result of the District successfully securing funding for reconstruction through the General Obligation Bond measure passed by voters in November 2016. 
     
    During the period of construction, access to the site is limited to those involved with construction work.

    If you have questions regarding the Skyline Reconstruction project - please call 858-794-3699 or email facilities@sbsd.k12.ca.us

      Architectural Rendering of the New Skyline Campus


    11/17/2017 Update:
    Work will proceed on site Saturday 11/18/2017. Concrete will be poured at the first floor classroom building. Concrete saw cutting will also occur.
    Small earth moving equipment will be used on site.
    Masonry began the week of November 13, 2017 and will continue on the first floor for appoximately three weeks.
    No workers will be on site for the Thanksgiving Holiday Weekend (11/23-11/25/2017).

    11/9/2017 Update:
    Work will proceed on site of Friday 11/10/17 and Saturday 11/11/2017. Concrete will be poured at the first floor building.
    Small earth moving equipment will be used on site.
    Masonry will begin the week of November 13, 2017.
     
    First Floor Foundation    First Floor Foundation
     
    10/17/2017 Update:
    Underground utilities for the building pads (plumbing and electrical) continue working west to east.
    Saturday work will be performed. Some large and small earth moving equipment will be used and possible concrete placement.
    Thank you for continuing to walk, cycle and drive with care on Lomas Santa Fe Drive.
     

    10/7/2017 Update:
    Underground utilities for the building pads (plumbing and electrical) continue working west to east.
    Saturday work will be performed. Some large and small earth moving equipment will be used.
    Concrete forms being prepared for a large concrete delivery Monday, 10/9.
    Center median work is almost complete - landscape, irrigation and pavers.
    Thank you for continuing to walk, cycle and drive with care on Lomas Santa Fe Drive.
     
    Forms for retaining wall     Underground electrical conduits
    Backside of retaining wall for 2-story buidling.                          Electrical conduits. Underground.
     

    9/18/2017 Update:
    Underground utilities for the first building pad (plumbing and electrical) continue working west to east.
    Saturday work will be performed. Some large and small earth moving equipment will be used.
    East, Center and West drives have been formed and concrete has been poured.
    The 36" storm drain running north/south through the project is complete. This storm drain directs water from the northern neighborhoods to the storm drain on Lomas Santa Fe Drive.
    Center median irrigation, pavers and planting work continues. Thank you for walking, cycling and driving with care on Lomas Santa Fe Drive.
    Skyline Site Underground and Footing progress
    Photo - west first story building underground and footings. Concrete deliveries for footings and retaining walls begin week of September 25, 2017.

    9/9/2017 Update:
    Underground utilities for the first building pad continue working west to east.
    Saturday work will be performed - no large equipment.
     

    8/30/2017 Update 
     

     The first building pad is ready for installation of underground utilities. No work is scheduled for Saturday, 9/2/2017.Site Pad


     8/23/2017 Update 

    Large crusher

    Off-site work on Lomas Santa Fe Drive will be completed 8/25/2017 (except landscape and pavers). All lanes on Lomas Santa Fe will be opened. The sidewalk will continue to be closed. Please continue to read and follow the posted instructions for safety. Construction crews are scheduled to start working 10 hour days (8/16/2017-8/25/2017) and work is scheduled for Saturday, 8/26/2017.


    8/16/2017 Update
    Off-site work on Lomas Santa Fe Drive will continue through 8/28/2017. The sidewalk will continue to be closed. Please continue to read and follow the posted instructions for safety.

    Construction crews are scheduled to start working 10 hour days (8/16/2017-8/25/2017) and work is scheduled for Saturday, 8/19/2017.


    8/4/2017 Update
    During this portion of the off-site work along Lomas Santa Fe from Solana Hills Drive to Glencrest Drive, the sidewalk will be closed. Pedestrians are to use the sidewalk on the south side of Lomas Santa Fe for this block. The contractor is making every effort to complete this phase of the construction prior to the start of the school year in late August.
     
    No Saturday work is on the schedule for the immediate future.
     
    Installation of the retaining wall at the field area is underway.

    7/13/2017 Update
    Site grading and off-site work is well underway. Please exercise caution when traveling along Lomas Santa Fe and observe all signage. Public safety is very important.
     

    6/30/2017 Update
    Construction workers may be on site for 10 hours per day as well as some Saturdays. As of this morning, remaining buildings to be demolished include Building A, Room 9, Hex C and Hex D. 
     

    6/29/2017 Update:
    Temporary fence was installed today at the perimeter of the property and approximately one-half of the school buildings have been demolished. Materials are being sorted for recycle. The site is being graded in anticipation of site retaining wall installation beginning in the next few weeks. 
     
    Work on Lomas Santa Fe Drive along the Skyline property is expected to commence 7/5/2017. Traffic control will be in place.

    6/23/2017 Update:
    The district completed moving the materials and furniture out of the school on schedule this week. The temporary classrooms on the lower playground have been removed.  Demolition of various site conditions are underway. Temporary fencing will be assembled and demolition of the school buildings will begin week of 6/26/17.  Demolition of the buildings and grading of the site is scheduled to take seven to eleven weeks. 
     
    Work on Lomas Santa Fe Drive along the Skyline property is expected to commence 7/5/2017. Traffic control will be in place.

    6/19/2017 Update:
    The reconstruction of Skyline School will begin this week. The district is actively moving materials and furniture off campus, will install security fencing and begin demolition. The old buildings will be demolished, and the new buildings will be constructed between June 2017 and August 2018.

    Construction is scheduled to start the week of 6/19. The district will comply with the City Ordinance hours of 7am-7pm Monday thru Friday. Demolition and fencing will commence mid next week. The district will comply with Air Quality Control Board regulations and any dust from the activities will be mitigated as much as possible during the course of construction.
    Activity Center Building


     

     

     

     

     

     
     
     
     GO Bond sign thanking supporters
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     Demolished Building B
     
     
     
     
     
     
     
     
     
     
     
     
     
    Demolition
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
    Here are some Frequently Asked Questions (FAQs) about the project - May 2017

    When will reconstruction take place?

    Reconstruction will begin just after school ends in June 2017. The old buildings will be demolished, and the new buildings will be constructed during the 2017-18 school year. The plan has the new buildings ready for occupancy for the start of the 2018-19 school year.

    Will the students stay on campus during construction?

    It is important to have students off campus during construction. This ensures student safety and shortens the construction timeline.

    San Dieguito built a temporary campus at Earl Warren for use during construction, why not do the same for Skyline?

    The Earl Warren campus is much larger that the Skyline campus. Trying to fit a temporary campus on the Skyline property while building the new facility would create safety and construction challenges. It would also lengthen the construction timeline by at least 50% and greatly increase costs.

    What options were explored for interim student housing?

    The District reviewed a range of options such as construction of temporary classrooms on the Solana Vista campus, moving all of the Skyline students to campuses in Carmel Valley, building a temporary campus on the parking lot at Skyline, and finding an off-site location for a temporary Skyline campus.

    Where will the Skyline students attend school during reconstruction?

    We have secured an agreement with San Dieguito Union High School District which will allow our district to use some of the temporary classrooms at Earl Warren Middle School for Skyline students. Unfortunately, San Dieguito is not able to leave all of those classrooms in place for us. They must remove many of the classrooms to complete environmental mitigation as a part of the construction of Earl Warren. We will be able to use enough classrooms to house the 4th through 6th grade program, but not the entire Skyline student population.

    Is it safe for Skyline students to attend school on the Earl Warren campus?

    We will work closely with our colleagues in San Dieguito to provide a safe and nurturing environment for the Skyline students. Security systems and equipment will be in place, and the Skyline students will not be in the same buildings, parking lots, or fields as the middle school students. The bell schedules will remain staggered to minimize traffic impacts.

    Where will the Global Education students attend school since there is not sufficient room at Earl Warren?

    We have classroom space that could be made available at Solana Highlands (one of our Carmel Valley schools) that can accommodate the eight Global Education classes during Skyline’s reconstruction. This will be temporary for the 2017-18 school year only, and the Global Education classes return to Skyline with the rest of the students when the school reopens for the 2018-19 school year.

    How will the Global Education students get to Carmel Valley?

    The District will provide transportation for students at no cost to the families. The Presbyterian church across the street from the current Skyline campus will be used for student pick-up and drop-off.

    Why move the Global Education program?

    Global Education is a multi-age program, so it is very important that the classes stay together. Our district is committed to ensuring Global Education stays intact for the school year during which Skyline will be under construction (2017-18).

    Do the Global Education teachers support this temporary relocation plan?

    Teachers from Global Education have been on the design team for the “new” Skyline. They support temporarily moving the program to Solana Highlands and are committed to supporting the students and families during that process.