• Solana Ranch Classroom Addition Summer 2018 - Completed August 2018

    If you have questions regarding the construction projects - please call 858-794-3699 or email facilities@sbsd.k12.ca.us

    Four new classrooms will be installed at Solana Ranch to accommodate student projections. Design drawings are underway and will be posted here once received.


    7/24/2018 Update:
     
    Three of the four new classrooms have arrived at Solana Ranch. The remaining classroom will arrive on site this week.
    Site work is underway - trenching, electrical, plumbing, low voltage, fire alarm and landscape.
    Buildings will be ready for occupancy the week of August 20, 2018.
     
    7/12/2018 Update:
     
    Expect the first of the four classrooms to arrive Saturday, July 14. The three remaining classrooms will arrive on site on various days over the next two weeks.
    Site work is underway - trenching, electrical, plumbing, low voltage, fire alarm and landscape.
     

    SAFETY MESSAGE - No Public Access to the construction area.

    During the period of the classroom installation, access to the area is limited to those involved with construction work.

    School Office will be open August 6, 2018 for Student Registration.

     
    Site work, trenching at Solana Ranch   Site work, trenching at Solana Ranch

    3/17/2018 Update:

    Below is a site plan of the new classroom buildings. Installation is scheduled to begin Mid-June 2018.

    Solana Ranch Site Plan