• See below for the status of various construction projects districtwide:
     
    District Office Child Development Center - Summer 2017Claw of Tractor over Building
    The district will be replacing the three portable classrooms (14, 15, and 16) that are beyond useful life located in the middle of the property. The classroom work is scheduled to begin the week of June 26, 2017. The three classrooms will be replaced with four new classrooms expected to arrive on site the week of July 17, 2017. The classrooms are expected to be ready for occupancy the week of August 14, 2017. Coastal Commission and CEQA environmental reviews are complete.
     
    7/7/2017 Update
    The demolition of the classroom buildings will continue through Friday, July 7, 2017.  Next week, work will include foundation grading and utilities (water, electrical, fire alarm, etc).
     
    7/3/2017 Update
    The demolition of the classroom building began 7/5/2017. The cleanup and disposal is expected to take 4 days.

     
    If you have questions regarding the construction projects - please call 858-794-3699 or email facilities@sbsd.k12.ca.us