Carmel Creek Modernization FAQs and Updates

Schedule, Process and Updates

Carmel Creek Modernization Project Underway - 5/12/2024

 

The Carmel Creek Campus will be closed from 6/1/2024 to 8/5/2024. See Map Below.

The City of San Deigo Fields will remain open.

CC Summer

 

 

Construction on the Carmel Creek School Modernization Project will begin on June 3rd, 2024, and continue through November of 2024

Project Scope 

  • Access control

  • Exterior painting

  • Fencing and gates alcoves

  • Flooring 

  • Fire alarm system replacement

  • Gates at the East and West of blacktop

  • Kitchen remodel

  • Interior ceiling repair and paint

  • Kindergarten playground artificial turf

  • Lunch structure maintenance 

  • Removal of portable building

  • Replace roofing

  • Replace skylights

  • Upgrade student garden

  • Staff lounge update 


Carmel Creek Modernization Update - April 25, 2024

Presentation - The attached presentation regarding the Carmel Creek Modernization was provided to the Board of Education meeting on April 25, 2025


Carmel Creek Modernization Update - December 12, 2023

Presentation - The attached presentation regarding the Carmel Creek Modernization was provided to the Board of Education meeting on December 13, 2023

 


Proposed Schedule

Design Phase: May 2023 - January 2024 
DSA: November 2023 - May 2024
Construction: June 2024 - November 2024