Skyline Reconstruction FAQs and Updates
Skyline Reconstruction Information and Frequently Asked Questions (FAQ)
If you have questions regarding the Skyline Reconstruction project - please call 858-794-3699 or email facilities@sbsd.k12.ca.us
10/16/2018 Update:
The Governing Board of the Solana Beach School District, Superintendent, Jodee Brentlinger,
and
Principal, Lisa Denham, cordially invite you to attend the
Ribbon Cutting Ceremony for the Skyline School Reconstruction Project - a project funded by Measure JJ.
All are welcome.
Ceremony to be followed by light refreshments and student-led tours.
No RSVP Necessary. For special accommodations, please call (858)794-7130.
Schedule:
The Kindergarten building was turned over to the district as scheduled on October 6th. Student first day in the new classrooms, following the move in activities, was Monday October 15th.
The Kitchen, Lunch Area, and Theater is scheduled to be turned over to the district October 30, 2018. The fields will continue to be under construction through December. Once the field turf is established, students will be able to access the fields - estimated in Spring 2019.
9/20/2018 Update:
Mark your calendars - Skyline's Ribbon Cutting Ceremony scheduled for October 25, 2018.
8/29/2018 Update:
Welcome back to school. We heard many positive comments about our new school.
Phase #1 - Building and some site work complete for school opneing
Phase #2 - Kindergarten Building (October 2018)
Phase #3 - Theater, Student Service Kitchen and Lunch Area (November 2018)
Fields expect to be ready for Skyline student use in Spring if turf is well-established
8/23/2018 Update:
Wow. It's been a busy few weeks! Furniture and classroom supplies arrived, landscape continues, solar panel wiring, elevator, fire alarm connections, signage, phone lines and network connectivity are all underway. Play area and parking lot striping is complete. School staff, with help from friends and family members, are setting up classrooms preparing to welcome families next week. Please check the Skyline page for school opening communication at /Page/9.
Photo 1 Above: black top play area at North
Photo 2 Above: classroom with furniture
Photo 3 Above: Front entrance receiving the finishing touch of signage "ADMINISTRATION"
8/9/2018 Update:
Landscape installation underway. Classrooms are receiving final clean and accessory installation. Furniture arrives for the classrooms over the next couple of weeks. Please check the Skyline page for school opening communication at /Page/9.
7/12/2018 Update:
Expect asphalt installation in the play area behind the classroom building the week of July 16.
Play structures and carpet have arrived and installation is underway.
6/28/2018 Update:
No work on Site July 4th, 2018
Interior finishes are well underway - teaching walls, whiteboards, drinking fountains (with bottle fillers), paint, tack panel for pinable surfaces, ceiling tiles, doors, windows, etc. Landscape to begin in early July. Asphalt play area in rear is scheduled to begin the week of July 16. Play structures and flooring (carpet and vinyl) is arriving early July. Construction crews continue to work 6 days a week.
We look forward to welcoming students and families on Monday, August 27 at the Mini Open House - meet teachers and see the awesome new classrooms! First day of school is Tuesday, August 28th. Link to Skyline's webpage and bell schedule.
Photo 1: Interior casework/teaching wall. Photo 2: Grading underway at north play area.
Photo 3: Covered walkway steel structure underway. Photo 4: South facing two-story classroom building.
5/21/2018 Update:
Interior finishes are underway - drywall, paint and t-grid for ceiling tiles. Foundations poured for student gathering seatwalls north of campus. Construction crews continue to work 6 days a week.
Photo 1: Seatwall foundations underway. Photo 2: Interior classroom space - drywall and paint.
Photo 3: Color Board Display at Skyline Village Open House May 18th.
4/23/2018 Update:
Asphalt at driveway and parking lot is underway. Roofing continues - both built-up and standing seam. Construction crews continue to work 6 days a week.
Photo 1: Skyline Classroom Building from West Photo 2: Skyline Classroom Building from East
4/5/2018 Update:
A traffic advisory: Solana Hills Drive Closure (provided by the City of Solana Beach)














12/21/2017 Update:



12/7/2017 Update:
- Monday 12-11-17 6:00 PM to 2:30AM Saw cut street and side walk panel grind and set trench plates begin to pot hole utilities
- Tuesday 12-12-17 6:00 PM to 2:30 AM excavate weld holes and begin to excavate service trench
- Wednesday 12-13-17 6:00 PM to 2:30 AM complete trench excavation and have SDG&E inspection
- Saturday 12-16-17 6:00 PM to 2:30 AM SDG&E crew will install gas service and work on RFS on existing gas service
- Schedule for paving to be determined
Please continue to exercise caution when driving, cycling, walking and jogging on and along Lomas Santa Fe Drive.







The first building pad is ready for installation of underground utilities. No work is scheduled for Saturday, 9/2/2017.
8/23/2017 Update

Off-site work on Lomas Santa Fe Drive will be completed 8/25/2017 (except landscape and pavers). All lanes on Lomas Santa Fe will be opened. The sidewalk will continue to be closed. Please continue to read and follow the posted instructions for safety. Construction crews are scheduled to start working 10 hour days (8/16/2017-8/25/2017) and work is scheduled for Saturday, 8/26/2017.
Construction crews are scheduled to start working 10 hour days (8/16/2017-8/25/2017) and work is scheduled for Saturday, 8/19/2017.
Construction is scheduled to start the week of 6/19. The district will comply with the City Ordinance hours of 7am-7pm Monday thru Friday. Demolition and fencing will commence mid next week. The district will comply with Air Quality Control Board regulations and any dust from the activities will be mitigated as much as possible during the course of construction.




When will reconstruction take place?
Reconstruction will begin just after school ends in June 2017. The old buildings will be demolished, and the new buildings will be constructed during the 2017-18 school year. The plan has the new buildings ready for occupancy for the start of the 2018-19 school year.
Will the students stay on campus during construction?
It is important to have students off campus during construction. This ensures student safety and shortens the construction timeline.
San Dieguito built a temporary campus at Earl Warren for use during construction, why not do the same for Skyline?
The Earl Warren campus is much larger that the Skyline campus. Trying to fit a temporary campus on the Skyline property while building the new facility would create safety and construction challenges. It would also lengthen the construction timeline by at least 50% and greatly increase costs.
What options were explored for interim student housing?
The District reviewed a range of options such as construction of temporary classrooms on the Solana Vista campus, moving all of the Skyline students to campuses in Carmel Valley, building a temporary campus on the parking lot at Skyline, and finding an off-site location for a temporary Skyline campus.
Where will the Skyline students attend school during reconstruction?
We have secured an agreement with San Dieguito Union High School District which will allow our district to use some of the temporary classrooms at Earl Warren Middle School for Skyline students. Unfortunately, San Dieguito is not able to leave all of those classrooms in place for us. They must remove many of the classrooms to complete environmental mitigation as a part of the construction of Earl Warren. We will be able to use enough classrooms to house the 4th through 6th grade program, but not the entire Skyline student population.
Is it safe for Skyline students to attend school on the Earl Warren campus?
We will work closely with our colleagues in San Dieguito to provide a safe and nurturing environment for the Skyline students. Security systems and equipment will be in place, and the Skyline students will not be in the same buildings, parking lots, or fields as the middle school students. The bell schedules will remain staggered to minimize traffic impacts.
Where will the Global Education students attend school since there is not sufficient room at Earl Warren?
We have classroom space that could be made available at Solana Highlands (one of our Carmel Valley schools) that can accommodate the eight Global Education classes during Skyline’s reconstruction. This will be temporary for the 2017-18 school year only, and the Global Education classes return to Skyline with the rest of the students when the school reopens for the 2018-19 school year.
How will the Global Education students get to Carmel Valley?
The District will provide transportation for students at no cost to the families. The Presbyterian church across the street from the current Skyline campus will be used for student pick-up and drop-off.
Why move the Global Education program?
Global Education is a multi-age program, so it is very important that the classes stay together. Our district is committed to ensuring Global Education stays intact for the school year during which Skyline will be under construction (2017-18).
Do the Global Education teachers support this temporary relocation plan?
Teachers from Global Education have been on the design team for the “new” Skyline. They support temporarily moving the program to Solana Highlands and are committed to supporting the students and families during that process.